Nepal, May 9 -- The ongoing construction of adding stands and floodlights at the Tribhuvan University Cricket Ground in Kirtipur is drawing applause from all around-deservedly so. Nepalis are not used to the kind of speed with which work is being done. A 10,000-seating-capacity parapet and six floodlights are contracted out for Rs437.7 million and Rs421.9 million, respectively. Originally slated to complete in 66 days by May 7, the parapet contractor has asked for two months' additional time with the Ministry of Urban Development, saying the recent heavy rainfall delayed work. In Nepal's construction history, project delays and cost overruns are routine. Against this, the TU work has come as a beacon of hope.

No country can move up the d...