Chitwan, May 8 -- Nearly a year after the ceremonial groundbreaking of the signature bridge over the Narayani River, construction has yet to begin.
Then prime minister Pushpa Kamal Dahal and minister for physical infrastructure and transport Raghubir Mahaseth performed the symbolic foundation-laying ceremony on May 14 last year at Narayanghat, but work has not commenced.
Krishna Acharya, spokesperson for the Bharatpur Division Road Office, stated that the bridge's design is still being finalised. Chinese experts recently inspected the site, but no further progress has been made. Tundi Construction Pvt Ltd has been assigned to build the bridge and prepare the design.
Lalijan Khanal, head of the bridge division at the Department of Roads...