JAMMU, Jan. 24 -- In the aftermath of incessant rainfall and heavy snowfall across various parts of the Jammu Division, Jammu Power Distribution Corporation Limited (JPDCL) has undertaken power restoration works on a war-footing to normalize electricity supply at the earliest.

As a result of restoration efforts, the power load of JPDCL has been progressively enhanced and has presently reached 944 MW, as against the normal average running load of approximately 1056 MW, reflecting significant improvement in supply conditions.

At the Sub-Transmission level, 165 out of 181 numbers of 66/33 kV lines have been restored. Further, 440 out of a total of 483 Receiving Stations, accounting for 91%stand restored.

Similarly, at the Distribution level...