JAMMU, Jan. 23 -- In view of incessant rainfall and heavy snowfall across various parts of the Jammu Division, the power demand of Jammu Power Distribution Corporation Limited (JPDCL) witnessed an unprecedented decline, dropping to 140 MW at around 04:00 am. Consequent upon sustained restoration efforts undertaken by JPDCL, the running load has since been progressively enhanced to 891 MW, as against the normal average running load of approximately 1150 MW. At the Sub-Transmission level, 161 out of 181 numbers of 66/33 kV lines have been restored. At the Distribution level, 740 out of 1373 numbers of 11 kV feeders have been restored and restoration of remaining accessible feeders is being undertaken on priority.