KISHTWAR, Jan. 31 -- 118 Road Construction Company (RCC) of 35 Border Road Task Force (BRTF), Project Sampark, of BRO has successfully restored road connectivity along the 112 km Kishtwar - Sansari stretch, including the road at 8,759 feet, reconnecting the Chenab Valley in Jammu & Kashmir with Himachal Pradesh.

22 - 23 January: Heavy snowfall of 4 - 5 feet blocked the road axis.

25 January: Fresh snowfall further disrupted connectivity.

26 January: BRO teams cleared 2.5 feet of snow, restoring access up to Sansari.

27 January: Another spell of snowfall again blocked the route.

28 - 30 January: Intensive clearance operations were launched, and within 72 hours, BRO cleared 3.5 feet of snow, fully reopening the road to Sansari.

The Kish...