India, Oct. 29 -- Larsen & Toubro's Power Transmission & Distribution (PT&D) business has secured multiple grid infrastructure orders in Saudi Arabia, including projects for a 380 kV substation and extensive transmission lines.
The first contract involves the construction of a 380/33 kV Gas Insulated Substation, incorporating hybrid GIS components, 380 kV transformers and reactors, along with systems for protection, control, automation, telecommunication, HVAC, and firefighting.
The second set of contracts covers the construction of 380 kV overhead transmission lines spanning more than 420 km in total.