Pakistan, Oct. 23 -- The Ministry of Information Technology and Telecommunication has assured the National Assembly Standing Committee that the Islamabad IT Park project will be completed by December 31, 2025, within the revised deadline. The update was shared during a meeting chaired by Syed Amin ul Haq, where the ministry confirmed that around 80 percent of construction work has already been completed. Officials highlighted that delays were mainly caused by changes in the Korean contractor and consultant, which temporarily slowed the project's pace.

The committee was informed that Prime Minister Shehbaz Sharif has directed authorities to ensure the project's completion within the current year, emphasizing its importance in boosting Pak...