Dar es Salaam, April 28 -- DODOMA: THE Tanzanian government said the capacity of its power plants has skyrocketed as the country continues to strengthen electricity generation through the various projects.

By April this year, Tanzania has recorded a significant increase in electricity production, according to the Energy Ministrys statement released today, April 28, in Dodoma.

In one year, the capacity of power plants connected to the National Grid has increased to 4,031.71 megawatts (MW) by April this year, an 86.6 percent increase compared to 2,138 MW in March 2024.

Speaking in Parliament in Dodoma today, April 28, 2025, while presenting the revenue and expenditure estimates for the Ministry of Energy for the 2025/2026 fiscal year, th...