Dar es Salaam, March 26 -- MWANZA: FIVE out of the nine containers of furniture for the newly built MV Mwanza Hapa Kazi Tu arrived in Mwanza on Monday, paving the way for their installation to begin.

The remaining containers are expected to arrive yesterday, according to the Project Manager, Mr Vitus Mapunda.

He explained that the furniture installation is a month-long process, which is part of the completion of the project, valued at over 100bn/-.

As of now, the project is 96 per cent complete.

“The installation should be finished as soon as possible because the handover of the project to the government, through the relevant shipping company, will take place by the end of May this year,” he said.

The next step will be th...