Dar es Salaam, Feb. 14 -- DODOMA: THE Parliamentary Public Accounts Committee (PAC) has expressed strong concern over serious irregularities in the implementation of the first phase of the Msalato Airport project, resulting in a loss of over 9bn/- due to mismanagement.

The committee also cited concerns about the projects value for money, given the over 600bn/- budget overseen by the Tanzania Roads Agency (TANROADS).

It tasked the government to review the provisions of the projects financing agreement. The review of an agreement according to PAC Chairperson, Naghenjwa Kaboyoka will help to balance the extra costs by ensuring that all unnecessary additional costs are paid by the side that occasions loss.

Ms Kaboyoka made the shocking rev...