Entebbe Airport expansion at 90 percent complete as passenger traffic rises
Uganda, April 20 -- The project for upgrade and expansion of Entebbe International Airport stands at 90 percent level of completion, the Uganda Civil Aviation Authority's (UCAA) Director General, Mr Fred Bamwesigye has said.
"The major remaining project is the 20,000 square meters terminal building, currently under construction to connect to the existing terminal building and is at 60 percent level of completion. Overall, the project works are at 90 percent level of completion. The other pending work is expansion of Apron 1, which is at 95 percent level of completion," Mr Bamwesigye said while addressing a press conference at Entebbe International Airport on Friday, April 19.
He said other earlier completed works under the $200 million ...
Click here to read full article from source
To read the full article or to get the complete feed from this publication, please
Contact Us.