Mumbai, March 3 -- The scope of the project includes designing, supplying, installing, testing, and commissioning a 25 KWp solar PV plant, along with an alternative lighting arrangement. The project also covers the construction of an RCC-framed structure for the control/battery room and CC pavement up to the control room for 10 Border Out Posts (BOPs) of 48 Bn (125 Bn), 51 Bn, 67 Bn, and 161 Bn BSF of SHQ Jammu under FTR HQ BSF Jammu, in accordance with site conditions. Additionally, the project includes five years of onsite maintenance and warranty.

The total value of the contract is Rs 3,09,35,413, and the facilities are expected to be completed within 12 months, starting 10 days after the letter of acceptance is received. The payment ...