Mumbai, April 2 -- According to an exchange filing, SGEL achieved this significant milestone on March 31, 2025. The capacity is now operational and is set to achieve Commercial Operation Date (COD) on 2 April 2025.
The Bikaner Solar Power Project, with a total planned capacity of 1,000 MW, is slated for full commissioning by 30 September 2025. Upon completion, SGEL will supply the generated solar power to three states: Rajasthan, Jammu & Kashmir, and Uttarakhand.
This project is expected to make a substantial contribution to India's goal of achieving 500 GW of non-fossil fuel capacity by 2030. It also aligns with SJVN's vision of becoming a 25,000 MW company by 2030 and 50,000 MW by 2040.