Mumbai, Feb. 22 -- The said contract involves Engineering, Procurement, and Construction (EPC) for the design, supply, erection, testing, and commissioning of the 2x25 KV OHE and PSI system. This includes the installation of Traction Substations (TSSs), Sectioning Posts (SPs), and Subsectioning Posts (SSPs), as well as Electrical General Services, Engineering, and Telecommunication works.

The project will cover the TK-RDG Section, spanning 99.463 Route Kilometers (RKM) or 114.145 Track Kilometers (TKM), between Rayadurga (Excl.) (CH: 205/463) and Topavagada (Incl.) (CH: 106/000).

The total cost of the project is Rs 156.35 crore, with an expected completion timeline of 18 months.

Rail Vikas Nigam is in the business of executing all type...