Mumbai, Feb. 28 -- The contract involves the design, supply, erection, testing, and commissioning of 132/55 KV Traction Substations, Sectioning Posts (SPs), and Sub-Sectioning Posts (SSPs) for the 2 x 25 KV Traction System (Scott Connected Transformer) on the Bhusaval-Khandwa sections of the Central Railway. This project aims to meet the 3000 MT loading target and will be executed under the Engineering, Procurement, and Construction (EPC) mode.
The total contract value is Rs 135.66 crore and the project is scheduled to be completed within 24 months.
Rail Vikas Nigam is in the business of executing all types of railway projects, including new lines, doubling, gauge conversion, railway electrification, metro projects, workshops, major bri...