Mumbai, July 12 -- The contract encompasses the design, supply, erection, testing, and commissioning of an overhead equipment (OHE) upgradation project. This involves converting the existing 1x25kV system to a 2x25kV feeding system, including associated feeder and earthing works.

The scope of work covers the Duvvada-Rajahmundry and Samalkot-Kakinada Port sections of the Vijayawada Division, falling under South Central Railway. The total length of the project spans 195.5 track kilometers (RKM) / 391 equivalent track kilometers (TKM).

The domestic contract has to be executed within a period of 24 months.

Rail Vikas Nigam is in the business of executing all types of railway projects, including new lines, doubling, gauge conversion, railwa...