Mumbai, July 12 -- The contract pertains to Package 1-CA-232 and involves a comprehensive scope of work, including the design, manufacture, supply, installation, integration, testing, and commissioning of rolling stock, communication-based signaling & train control, telecommunication systems, platform screen doors, and depot machinery & plant for Line 6 [Swami Samarth Nagar to Vikhroli - (EEH)] of the Mumbai Metro Rail Project.

The execution timeline includes a 24-month construction period, followed by a 2-year Defect Liability Maintenance Period (DLMP), and an additional 5 years of comprehensive maintenance post-DLMP.