Mumbai, Sept. 15 -- As per L&T's order classification, a large order falls in the range of Rs 2,500 crore to Rs 5,000 crore. The contract pertains to Package T1, which spans from Mumbai's Bandra-Kurla Complex to Zaroli village near the Maharashtra-Gujarat border.

The project includes the design, supply, construction, testing, and commissioning of track-works on a design-build lump sum price basis. The scope covers over 21 km of underground tracks, aligned with civil packages C1 and C2, and 135 km of elevated viaduct sections under package C3.

The track system will utilize the Japanese Shinkansen J Slab Track Technology, designed to support train speeds of up to 320 kmph. The technology is known for offering better ride quality, increase...