Mumbai, Aug. 4 -- The plant is situated in Chamba district of Himachal Pradesh. The project has commenced power dispatch to the Haryana Power Purchase Centre.
The second 80 MW unit has already been synchronised with the grid and is undergoing trial run, while the last unit is expected to be synchronised soon.
The Kutehr project is backed by a long-term power purchase agreement with Haryana Power Purchase Centre (HPPC) for the entire 240 MW at a levelized ceiling tariff of Rs 4.50 per kWh, valid for 35 years with provisions for extension.
Power generated will supply Haryana's state distribution utilities - Uttar Haryana Bijli Vitran Nigam and Dakshin Haryana Bijli Vitran Nigam.
With this capacity addition, the installed hydro capacity ...