Mumbai, March 17 -- The contract is for the construction of an 8.65 km underground metro corridor, including tunnels and stations, for the Indore Metro project.
This Package IN-05R represents the first and only underground segment of the 31.32 km Indore Metro Phase-1 project.
It involves the construction of 11.32 km of tunnels using Tunnel Boring Machines (TBMs) and seven underground stations: Indore Railway Station, Rajwada, Chota Ganpati, Bada Ganpati, Ramchandra Nagar, BSF/Kalani Nagar, and Airport. The corridor will connect a ramp east of Indore Railway Station to a ramp west of Airport Station.
Currently, HCC is also involved in the construction of 4 km of twin tunnels and four stations for Mumbai Metro Line III, as well as two pa...