Mumbai, Feb. 24 -- The project entails widening the Raipur-Jassakhera stretch (Km 0.000 to Km 29.770) of NH-458 in Rajasthan under the EPC (engineering, procurement, and construction) model. The total contract value is Rs 397 crore, with a scheduled execution period of 30 months.
The scope of work includes converting the highway to a two-lane configuration, constructing paved shoulders, multiple bridges, and ancillary road works such as drains and culverts.
The project aligns with Brahmaputra Infrastructure's core EPC operations, particularly in road and transportation infrastructure.
With this award, Brahmaputra Infrastructure's total order book, including joint operations, now stands at approximately Rs 1,500 crore. The current order...