Mumbai, Nov. 10 -- The order, awarded by the President of India through the chief electrical engineer (CEE)/project, NWR, Ajmer, involves the upgradation of the existing electric traction system from 1 x 25 kV to 2 x 25 kV. The project also includes modification of the overhead equipment (OHE) to support train operations at speeds of up to 160 kmph across select sections of Ajmer Division, covering AII-COR, COR-UDZ, MD-BWA, and BWA-PNU sections, spanning a total of 660.81 route km (1,200.85 track km).
The scope of work includes design, supply, erection, testing, and commissioning. The contract is to be executed domestically over 24 calendar months from the date of issuance of the letter of acceptance (LoA).
There is no interest from Ash...