Mumbai, Feb. 19 -- The project forms part of 380 MW capacity, of which PPA for the first 190 MW has already been signed. The hybrid project will include 190 MW inter-state transmission system (ISTS)-connected wind solar hybrid power project with battery energy storage system (BESS) for assured peak power supply, at a tariff of Rs 4.72 per unit.
The PPA requires supplying power with minimum annual Capacity Utilisation Factor (CUF) of 50% and an obligation to meet 80% of peak power requirement on daily basis.
This project has already been financed by Power Finance Corporation (PFC) as part of the existing sanctioned project under Phase II.
The PPA tenure is 25 years from the date of signing of PPA, with scheduled commercial operation dat...