Mumbai, Nov. 20 -- With this phase, the project's operational capacity now stands at 44 MW, contributing to ACME Solar's overall operational portfolio rising to 2,934 MW.
Officials from the Gujarat Energy Development Agency (GEDA) and Paschim Gujarat Vij Company (PGVCL) witnessed and confirmed the commissioning. The formal certificate is expected to be issued shortly. The remaining capacity will be commissioned in phases.
The company recently received an extension to the project's Scheduled Commercial Operation Date (SCOD) from the Gujarat Electricity Regulatory Commission (GERC) after Force Majeure events under the power purchase agreement (PPA) were recognised. The revised SCOD is now 5 March 2026. ACME Solar has already achieved earl...