Srinagar, Jan. 24 -- KPDCL machinery is deployed in the field and working with full efficiency and determination to restore power supply to all affected areas. According to the official statement by KPDCL, high-speed gusty winds and heavy Snowfall have severely damaged the electrical network in many locations. Restoration could not be undertaken yesterday in several areas due to road blockades caused by heavy snowfall and limited accessibility. The restoration process, which is being carried out on a war footing, is exhaustive in nature and involves clearing dismantled rooftops from electrical lines, repairing HT and LT networks, and replacing damaged distribution transformers (DTs). At the sub-transmission level, 120 out of 135 numbers o...