Australia, May 25 -- New South Wales Land and Environment Court issued text of the following judgement on April 24:
1. On 16 August 2023 the plaintiff, Nexus Access Pty Ltd (Nexus), obtained default judgment against the defendant, CH Pacific Resources Pty Ltd (CPR), on its Amended Statement of Claim (ASoC) in the sum of $100,234.59. By notice of motion filed 21 February 2025, CPR seeks to set aside that judgment and to set aside a number of consequential orders. The orders sought to be set aside include a garnishee order and CPR seeks the return of $74,488.25 garnisheed from its bank account on 31 August 2023.
2. CPR says the default judgment ought be set aside under r 36.15 of the Uniform Civil Procedure Rules 2005 (UCPR) on the basis th...