Ayodhya, May 2 -- The Ram Janmabhoomi Temple Construction Committee began a three-day meeting in Ayodhya to review the progress of the temple construction. On the first day, committee president Nripendra Mishra provided major updates on the construction.

He stated that inspections were conducted at various locations within the temple, and that most of the construction (except for an auditorium and a wall) is expected to be completed by December 2025.

"Except for constructing a four-kilometre boundary wall and the auditorium, all other constructions will be completed by December 2025," committee president Mishra remarked.

Most idols have already reached their respective temples. Only two idols- one for the Ram Darbar and another for the...