New Delhi, July 14 -- The bullet train project has achieved a major milestone of opening the first section of the 21 km undersea tunnel between BKC and Thane, according to an official release from the Ministry of Railways.
The bullet train project recently achieved a major milestone by completing 310 km of viaduct construction. Track laying, construction of overhead electrical wires, stations, and bridges are going on at a rapid pace. The construction work in Maharashtra has also picked up pace. In parallel, the progress on the procurement of systems for operations and control is also going well, the release highlighted.
In the spirit of strategic partnership between Japan and India, the Japanese government has agreed to introduce E10 S...