Thimphu, Aug. 28 -- The 1020 MW Punatsangchhu-II Hydroelectric Project in Bhutan has been successfully completed with the synchronisation of its last and final unit, Unit 6 (170 MW), with the power grid, the Embassy of India in Thimphu said on Wednesday.

"Today, with the synchronisation of the last and final unit [Unit 6 (170 MW)] with the power grid, the 1020 MW Punatsangchhu-II Hydroelectric Project achieved its successful completion. A ceremony was held at the project's powerhouse to mark the occasion," the Embassy of India in Thimphu said.

Dasho Tshering Tobgay, Prime Minister of Bhutan; Lyonpo Gem Tshering, Minister of Energy & Natural Resources, Royal Government of Bhutan; Ambassador of India to Bhutan, Sudhakar Dalela; Anurag Aga...