Aurangabad, Feb. 11 -- In a significant milestone under NTPC Nabinagar's Stage-II expansion, the first column of Unit 4 Boiler was laid on Wednesday at the NTPC Nabinagar, under which three units of 800 MW are being constructed to boost Bihar's self-reliance in energy.

After installation of the first column, Regional Executive Director (ER-1), NTPC ltd. Vijay Goel inspected the Stage-II construction area along with L.K. Behera, Head of Project, NTPC Nabinagar.

According to a release of the NTPC, during the visit, he reviewed the progress of construction work in coordination with officials from the Project Construction Department and L&T. He appreciated the dedication and commitment of all departments in completing this important phase wit...