United States, March 26 -- Steward Machine Co. Inc., Birmingham, Alabama, was awarded a firm-fixed-price contract for fabrication and delivery of Coffeeville Lock lower miter gates and spare parts for the Black Warrior-Tombigbee Project Office. The amount of this action is $14,636,870 with a total cumulative face value of $16,814,219. Bids were solicited via the internet with four received. Work will be performed in Birmingham, Alabama, with an estimated completion date of July 19, 2029. Fiscal 2026 operations and maintenance, Corps of Engineers, Civil funds in the amount of $14,636,870 were obligated at the time of the award. U.S. Army Corps of Engineers, Mobile District, is the contracting activity (W91278-26-C-A012).