Navi Mumbai, May 16 -- Navi Mumbai Municipal Corporation has set May 25 deadline to complete premonsoon work.

Civic commissioner Ramaswamy N has ordered all digging work to stop and instructed the agencies. By May 30, the agencies should repair the roads dug by them.

As the head of the disaster management committee, Ramaswamy on Wednesday undertook a detailed review of the pre-monsoon work undertaken.

Additional municipal commissioner Ravindra Patil, member secretary of the committee, gave a presentation of the measures taken and the action report.

Ramaswamy said, "I have ordered that the pre-monsoon gutter and nullah cleaning work should be completed by May 25. There are six nullah cleaning tenders that were delayed due to the code of ...